The scaffolding is coming down at one of the most closely watched sites in west Hanoi. In November 2026, main contractor Ricons said Starlake The Prime K8HH1 had moved fully into the finishing stage, with interior and exterior trades now working side by side in the office tower, the two residential towers and the supporting areas.
For anyone weighing a purchase in Starlake Tay Ho Tay, this matters for more than one reason. K8HH1 is the first part of The Prime, the second wave of homes that Daewoo E&C is building in the township. Its finishes, its timetable and its quality will also be the best real-world preview of The Prime K8CT1, the larger sister phase that is now coming to market.
Where K8HH1 Stands in November 2026
The drone photos released with Ricons’ update show both residential towers and the office tower at full height. Most of the office tower’s glass curtain wall is in place, and work has moved to the podium, the landscaping and the external works at ground level.
In its update, Ricons said every item is gradually being finished, and that this stage calls for close coordination between its team and the other contractors to deliver the project on schedule.
From Basement to Handover: The Construction Path
- Basement and superstructureCompleted: the two apartment towers and the office tower stand at full height.
- Facade and rough finishingLargely in place, led by the glass curtain wall of the office tower.
- Interior finishing and MEPUnder way in all three towers and the supporting areas (November 2026).
- Testing, acceptance and handoverThe next stage. Dates are to be confirmed by the developer.
Ricons holds a broad package on the site: the basement and superstructure, rough finishing and the facade, the installation of the mechanical, electrical and plumbing (MEP) systems, and the technical infrastructure. Having one contractor carry the building from the basement to the facade usually makes the last months of a project easier to manage, because fewer handovers between contractors are needed.
Why the Finishing Stage Matters to Buyers
In Vietnam’s off-plan market, the end of structural work is a turning point. Once the towers stand at full height, the biggest construction risk is largely behind the project. What remains is quality and timing: how well the apartments are finished, whether the lifts, fire safety and air-conditioning pass testing on time, and how quickly the developer can hand over keys and then issue ownership certificates.
These are the points we would check at this stage:
- The handover date in the sale and purchase agreement, and the penalty for delay
- The finishing schedule (brands of fittings, flooring and kitchen appliances) against the show flat
- Testing and approval of MEP and fire safety systems before handover
- The defects liability period and how claims are handled
- The timeline for issuing ownership certificates (pink books)
Starlake’s first-phase apartment towers (901, 902 and 903) are already completed and lived in, so buyers can visit finished buildings in the same township and judge the developer’s standards for themselves. You can browse current resale and rental units there on our Starlake apartments page.
One Brand, Two Phases: K8HH1 and K8CT1
The Prime is the name Daewoo E&C uses for the high-end apartments in the second phase of Starlake. It spans two plots, and the difference between them is easiest to see side by side:
| K8HH1 | K8CT1 – West Lake Edition | |
|---|---|---|
| Plot type | Mixed-use | Residential |
| Towers | 2 residential + 1 office | 4 residential (K8A–K8D) |
| Height | 26 storeys (residential), 20 storeys (office) | 23 storeys |
| Apartments | 284 | 656 |
| Basements | — | 2 connected levels |
| Main frontage | Central area of Starlake | Vo Chi Cong Street |
| Foreign buyers | — | Up to 30% in Towers B, C and D |
| Status (Nov 2026) | Finishing works | Preparing for launch |
This is why the progress at K8HH1 matters to anyone looking at Starlake The Prime K8CT1. The two phases share a developer, a brand, a design language and a neighbourhood. K8HH1 is, in effect, a full-scale sample of what K8CT1 buyers can expect, and it is visible from the street today.
The Prime K8CT1 – West Lake Edition
The larger, purely residential phase of The Prime, on Vo Chi Cong Street.
- 4 towers, 23 storeys. K8A, K8B, K8C and K8D, above two connected basement levels
- 656 apartments. from one-bedroom homes to four-bedroom units and penthouses
- Vo Chi Cong frontage. quick access to West Lake, Nhat Tan Bridge and Noi Bai Airport
- Resort-style facilities. indoor and outdoor pools, gym, indoor golf and a children’s play area
Starlake Around K8HH1
K8HH1 is not rising in isolation. Across Starlake’s 186.6 hectares, the commercial core is already working: the Shilla Monogram hotel and the IFC Hanoi towers are open, and Thiso Mall – Emart and Westlake Square Hanoi, developed by Takashimaya, are scheduled to open in the second quarter of 2027. Only about 16% of the township’s land is set aside for housing, which keeps the supply of new homes limited.
Roads and public transport are also catching up, and a new government quarter is planned on 35 hectares at the heart of the township. We look at these changes in detail in our companion piece: West of West Lake Enters a New Growth Phase.
Our View
For several years, The Prime existed mainly as renders and sales brochures. With K8HH1 now in finishing works, the second phase of Starlake has become something buyers can walk around and inspect. That makes it easier to judge K8CT1 on evidence rather than promises: the same developer, the same brand and the same street grid, only on a larger plot and with a frontage on Vo Chi Cong Street.
We will keep following K8HH1 through handover. If you would like the latest price list, floor plans or foreign-quota availability for The Prime K8CT1, contact the Kensington team below.