Hanoi plans seven ring roads, and several reached milestones in 2026. The long-delayed Hoang Cau – Voi Phuc section of Ring Road 1 opened on 2 September 2026, a section of Ring Road 2.5 followed in October, and part of the 113.5 km Ring Road 4 opened the same month. Ring Road 4’s expressway and bridges are due in 2027, and the 349 km Ring Road 5 was approved in August 2026.
Key takeaways
- Ring Road 1. Hoang Cau – Voi Phuc opened 2 September 2026; two flyovers due by the end of 2026.
- Ring Roads 2 and 3. Complete loops, with elevated sections (Ring Road 2 elevated deck opened January 2023).
- Ring Road 3.5. Under construction, including the Thuong Cat and Ngoc Hoi bridges; the ring that has changed housing most.
- Ring Road 4. 113.5 km through Hanoi, Hung Yen and Bac Ninh; parallel road partly open, expressway 37%, bridges due 2027.
- Ring Road 5. 349 km, approved August 2026; construction from 2027.
What Are Hanoi’s Ring Roads?
| Ring road | Route | Status (November 2026) |
|---|---|---|
| Ring Road 1 | Inner arc around the historic core: Dai Co Viet, Xa Dan, De La Thanh, Hoang Cau and the riverside Tran Khanh Du – Tran Quang Khai – Yen Phu | Hoang Cau – Voi Phuc (2.2 km) opened 2 Sep 2026; two flyovers due by end 2026 |
| Ring Road 2 | Vinh Tuy – Minh Khai – Nga Tu Vong – Nga Tu So – Cau Giay – Buoi – Nhat Tan bridge – Dong Anh – Vinh Tuy | Complete loop; elevated deck Vinh Tuy – Nga Tu So opened 11 Jan 2023 |
| Ring Road 2.5 | Between Ring Roads 2 and 3, in sections (e.g. Nguyen Trai – Dam Hong, Tay Ho Tay) | Nguyen Trai – Dam Hong (1.52 km) technical opening 10 Oct 2026; other sections in progress |
| Ring Road 3 | Mai Dich – Thanh Xuan – Phap Van – Thanh Tri bridge – Sai Dong – Ninh Hiep – Dong Anh – Nam Hong | Complete loop; elevated Mai Dich – Nam Thang Long opened 2020 |
| Ring Road 3.5 | Outer ring linking new urban areas, crossing the Red River on the Thuong Cat and Ngoc Hoi bridges | Under construction in sections |
| Ring Road 4 – Capital Region | 113.5 km through Hanoi (57.5 km), Hung Yen and Bac Ninh | Hanoi parallel road about 90%, 14 km opened 10 Oct 2026; expressway 37% |
| Ring Road 5 – Capital Region | About 349 km through seven provinces | Approved 24 Aug 2026; construction from 2027 |
What Changed on Ring Roads 1 and 2.5 in 2026?
The 2.2 km Hoang Cau – Voi Phuc section of Ring Road 1, a 50 m wide road through Dong Da costing about VND 7.2 trillion, opened to traffic on 2 September 2026 after years of land clearance (VietnamPlus). Two flyovers on it, at Lang Ha – Giang Vo and Nguyen Chi Thanh, are still being built, with a deadline of the end of 2026 (CafeF / Dai Doan Ket).
On Ring Road 2.5, the 1.52 km Nguyen Trai – Dam Hong section, which cost more than VND 2.4 trillion and includes an underpass at Giai Phong, had its technical opening on 10 October 2026, and a section in Tay Ho Tay opened at the end of September (VietnamPlus). Ring Road 2’s elevated deck from Vinh Tuy to Nga Tu So has been open since January 2023 (VnEconomy).
What Is Being Built on Ring Road 3.5?
Ring Road 3.5 runs outside Ring Road 3 and is meant to link a chain of new urban areas. Its two new Red River crossings, the Thuong Cat and Ngoc Hoi bridges, are both under construction with 2027 targets; see our guide to Hanoi’s new Red River bridges. On the city side, the 3.5 km section from Thuong Cat bridge to Highway 32 (about VND 1.5 trillion) was at an early stage in October 2026, with land handed over at the Tay Thang Long junction (CafeF / Dai Doan Ket).
When Will Ring Road 4 Be Finished?
Ring Road 4 – Capital Region is about 113.5 km long, of which 57.5 km in Hanoi, 19.3 km in Hung Yen and 35.7 km in Bac Ninh, with a total budget of VND 85.8 trillion from central, local and private (BOT) funds. The expressway is designed for 100 km/h with four lanes at first, and has eight interchanges, five of them in Hanoi (VietnamPlus).
Progress is uneven. In Hanoi, land clearance is complete and the parallel road was about 90% built in October 2026; a 14 km stretch from the Huu Hong dike to Thang Long Avenue opened on 10 October 2026 (VOV). The expressway itself was 37% complete. The city wants its three big bridges, Hong Ha and Me So over the Red River and Hoai Thuong over the Duong, open before the APEC meetings in 2027 (CafeF / Dai Doan Ket).
What Is Ring Road 5?
Ring Road 5 – Capital Region is an outer ring of about 349 km through Hanoi, Ninh Binh, Hung Yen, Hai Phong, Bac Ninh, Thai Nguyen and Phu Tho. The National Assembly approved it on 24 August 2026 at about VND 288 trillion. Construction is due to start in 2027, with 116 km of expressway by 2030 and the whole route before 2035 (The Leader). Older plans gave a shorter route of about 330 km through eight provinces, before Vietnam merged its provinces in 2025. Excluding stretches shared with existing expressways, the new route is about 321 km, mostly six lanes, with four lanes through Thai Nguyen.
What Role Does Each Ring Road Play in the Master Plan?
The 100-year Capital Master Plan approved in May 2026 (Decision 2512/QD-UBND) commits the city to completing Ring Roads 4, 4.5 and 5 (VietnamPlus). It also gives each ring a role. Ring Roads 1, 2 and 2.5 serve the historic core; Ring Road 3 is meant to mark the edge of a compact city, with public transport hubs and fewer private cars entering the centre; Ring Road 3.5 links a chain of new urban areas; and Ring Roads 4 and 5 connect Hanoi with the surrounding provinces (Vinhomes Market, November 2026).
See also our guides to the Hanoi metro, Hanoi’s 2026–2030 mega-projects and Hanoi’s 100-year master plan.
Do Ring Roads Raise Property Prices?
They can, mainly for landed homes. CBRE reported that landed homes in Hanoi averaged VND 247 million/m² in Q3 2026, up 33% year on year, with new supply concentrated along Ring Roads 3 and 3.5, while new apartment prices eased by 6% (VietnamPlus / CBRE). A ring road helps a project only if there is an interchange nearby and the local roads connect to it; distance on a map is not enough.
From our experience at Kensington
- Ring Road 3.5 has changed housing the most. Many projects have been built or are under way along it, especially in Hoai Duc, which used to be seen as a distant suburb.
- Ring Road 4 is about industry for now. It connects the Capital Region and mainly serves industrial parks and logistics. Because it is not finished, we have not yet seen a big effect on housing.
- Check the interchange, not the map. When a seller says a project is “on the ring road”, ask where the nearest on-ramp is and whether it is open yet.
Frequently Asked Questions
How many ring roads does Hanoi have?
Hanoi plans seven: Ring Roads 1, 2, 2.5, 3, 3.5, 4 and 5. Ring Roads 2, 3, 4 and 5 are full loops, while 1, 2.5 and 3.5 are open arcs serving the city south of the Red River. Ring Roads 2 and 3 are complete, 4 is being built, and 5 was approved in August 2026.
Is Ring Road 1 finished?
Mostly. The Hoang Cau – Voi Phuc section in Dong Da, about 2.2 km, opened to traffic on 2 September 2026 after years of land clearance. Two flyovers on it, at Lang Ha – Giang Vo and Nguyen Chi Thanh, are due by the end of 2026.
What is Ring Road 4?
Ring Road 4 – Capital Region is a 113.5 km expressway with parallel roads through Hanoi, Hung Yen and Bac Ninh, costing about VND 85.8 trillion. Part of the Hanoi parallel road opened in October 2026; the expressway was about 37% complete and its big bridges are due in 2027.
When will Ring Road 4 be finished?
The city aims to open its three big bridges, Hong Ha, Me So and Hoai Thuong, before the APEC meetings in Hanoi in 2027. The Hong Ha and Me So bridges are due to be completed in October 2027; no final date has been announced for the whole expressway.
What is Ring Road 5?
An outer ring of about 349 km through seven provinces around Hanoi, costing about VND 288 trillion. The National Assembly approved it on 24 August 2026; construction is due to start in 2027, with 116 km of expressway by 2030 and the full route before 2035.
Do ring roads raise property prices?
They can. CBRE reported that landed-home prices in Hanoi rose 33% year on year in Q3 2026, with new supply concentrated along Ring Roads 3 and 3.5. In our experience Ring Road 3.5 has driven housing development, for example around Hoai Duc.
Which ring road matters most for expats?
For daily life, Ring Roads 1 to 3 inside the city. Ring Road 3 links Cau Giay, My Dinh, Thanh Xuan and Linh Dam, and its elevated section is the fastest way across the west of the city. Ring Roads 4 and 5 mainly matter for industry and trips to other provinces.
Sources
- Ring roads: VietnamPlus (2 September 2026), VnEconomy (11 January 2023), VietnamPlus (10 October 2026), CafeF / Dai Doan Ket (8 October 2026), VietnamPlus (19 August 2026), VOV (10 October 2026), The Leader (25 August 2026)
- Plans and routes: VietnamPlus (May 2026), Vinhomes Market (20 November 2026)
- Prices: VietnamPlus / CBRE (17 October 2026)
Comparing areas along the ring roads?
Tell us where you work and your budget. We will tell you how a ring road really affects the commute from each building, and which projects have an interchange that is open today.
About the author
Harry Nguyen is Co-Founder and Executive Director of Kensington Vietnam and a licensed real estate broker (certificate HN-2621, Hanoi Department of Construction). For more than 10 years he has helped foreigners rent and buy homes in Hanoi. Harry’s profile and listings
Update log: 27 November 2026 – first published, with a status tracker for Ring Roads 1 to 5.