By Harry Nguyen, Co-Founder & Executive Director, Kensington Vietnam · Updated 27 November 2026
Hanoi is building seven new bridges across the Red River at the same time, and most are due to open in 2027. Tran Hung Dao (Hoan Kiem – Long Bien) is furthest along, at 54% in November 2026, with a deadline of 30 June 2027. Tu Lien (Tay Ho – Dong Anh) is at about 27%, with a target of September 2027. Together they will give the city side of the river its first new crossings in years.
Key takeaways
- Seven bridges. Tran Hung Dao, Tu Lien, Ngoc Hoi, Thuong Cat, Van Phuc, Hong Ha and Me So, all started in 2025; targets mid-2027 to end-2027.
- Furthest along. Tran Hung Dao 54.2% (deadline 30 June 2027); Hong Ha 51%; Me So 48.7%.
- Tu Lien. 26.85% at the end of October 2026; technical opening targeted before 2 September 2027.
- Why it matters. Today’s car crossings (Chuong Duong, Vinh Tuy, Nhat Tan) are overloaded at peak hours, which keeps most foreigners on the city side of the river.
- For residents. New bridges add choice and lower prices across the river; we do not expect a mass move away from the centre.
Which New Bridges Are Being Built Across the Red River?
| Bridge | Connects | Size and cost | Started | Progress | Target |
|---|---|---|---|---|---|
| Tran Hung Dao | Hoan Kiem (Cua Nam) – Long Bien (Nguyen Son St) | 4.18 km, 6 lanes; about VND 16.2 trillion (PPP, Sun Group consortium) | 9 Oct 2025 | 54.2% (6 Nov 2026) | Before 30 Jun 2027 |
| Tu Lien | Tay Ho (Nghi Tam) – Dong Anh (Truong Sa road) | 5.15 km, 500 m main span, 6 lanes + 2 mixed; about VND 19.8 trillion | 19 May 2025 | 26.85% (end Oct 2026) | Before 2 Sep 2027 (technical opening) |
| Ngoc Hoi | South Hanoi – Hung Yen, via Bat Trang | About 7.5 km, 6 + 2 lanes; VND 11.8 trillion | 19 Aug 2025 | About 25.5% (Oct 2026) | Aug 2027 |
| Thuong Cat | Thuong Cat – Thien Loc (Ring Road 3.5) | Cable-stayed, about 4.06 km bridge (5.22 km with approaches), 8 lanes; over VND 7.3 trillion | 8 Oct 2025 | 16.2% (21 Oct 2026) | Jul 2027 |
| Van Phuc | Phuc Tho (Highway 32) – Phu Tho | 7.77 km; VND 3.4 trillion | 19 Aug 2025 | 28.4% (1 Jul 2026) | Q4 2027 |
| Hong Ha (Ring Road 4) | O Dien – Me Linh | About 4.4 km bridge and viaduct, 4 + 2 lanes; about VND 10 trillion | Oct 2025 | About 51% (end Oct 2026) | Opening Jul 2027 |
| Me So (Ring Road 4) | Hong Van (Hanoi) – Van Giang (Hung Yen) | Over 2 km bridge, 4 + 2 lanes | 2025 | About 48.7% (19 Oct 2026) | Oct 2027 |
When Will the Tran Hung Dao and Tu Lien Bridges Open?
Tran Hung Dao bridge starts at the five-way junction near the Opera House and lands at Nguyen Son street in Long Bien, with an 870 m river crossing of six steel arches. It is built by a Sun Group-led consortium under a public-private partnership (The Investor). All river piers are finished, and it reached 54.2% by contract value in the city’s report of 6 November 2026, with a deadline of 30 June 2027 (CafeF / Tien Phong).
Tu Lien bridge runs from Nghi Tam in Tay Ho to Truong Sa road in Dong Anh, next to Vinhomes Global Gate. Its cable-stayed main bridge is 1,000 m long, with a 500 m span between two 185 m pylons. Work started on 19 May 2025 (Nha Dau Tu), and by the end of October 2026 it was 26.85% complete. The city wants a technical opening before 2 September 2027, but in August 2026 the city council called progress too slow, and the Nghi Tam interchange was held up by dike rules.
What About the Other Five Bridges?
The other five are further from the centre. Ngoc Hoi links south Hanoi with Hung Yen via Bat Trang (CafeF / Ha Noi Moi). Thuong Cat, a cable-stayed bridge on Ring Road 3.5, links the north-west of the city with Dong Anh (CafeF / Tien Phong). Van Phuc crosses in the far west towards Phu Tho (VietnamFinance). Hong Ha and Me So carry Ring Road 4 over the river and are the most advanced after Tran Hung Dao (CafeF / Tien Phong). For the ring roads themselves, see our guide to Hanoi’s ring roads.
Why Does Crossing the River Matter So Much Today?
Most foreigners in Hanoi live on the city side of the Red River, in Tay Ho, Ba Dinh, Hoan Kiem, Cau Giay or Nam Tu Liem. The east and north banks, Long Bien, Gia Lam and Dong Anh, offer newer townships and lower prices, but getting across is the problem.
Today, cars from the centre to Long Bien mostly use Chuong Duong or Vinh Tuy bridges. The historic Long Bien bridge carries only motorbikes, bicycles and trains, and Vinh Tuy is some way south of the centre. At peak hours Chuong Duong and Vinh Tuy are regularly overloaded, and Nhat Tan, the main route to Noi Bai airport, is showing the same strain. The second Vinh Tuy bridge, opened in August 2023, helped but did not solve it (VnExpress).
Tran Hung Dao will give the Old Quarter and Hoan Kiem a direct link to Long Bien, and Tu Lien will give Tay Ho a second crossing next to Nhat Tan.
How Many Bridges Will Hanoi Eventually Have?
Hanoi’s transport plan to 2030, with a vision to 2050, counts 18 bridges across the Red River. About half were already in use in 2025 and seven more started that year; the city has since added proposals for further privately funded bridges (Tien Phong). The 100-year Capital Master Plan approved in May 2026 (Decision 2512/QD-UBND) gives priority to multi-level tunnels under the river for roads and metro (VietnamPlus). We have not seen an official final count of bridges in that plan.
See our guides to the Red River plan, the Hanoi metro and Hanoi’s 100-year master plan.
Will the New Bridges Change Where Foreigners Live?
Somewhat. Once Tran Hung Dao and Tu Lien open, Long Bien and Dong Anh will be much quicker to reach from the centre, and we expect more foreign tenants and buyers to look there. Prices in Long Bien have already risen; some parts of Dong Anh still have room to grow. Savills notes that new apartment supply in Hanoi is moving outside the inner city, including to Dong Anh (Phap Luat / Savills, March 2026).
From our experience at Kensington
- Crossing the river is the barrier. Many of our clients hesitate to live across the river because the only practical car crossings today are Chuong Duong and Vinh Tuy, both overloaded at rush hour. Nhat Tan is starting to clog at peak times too. Hanoi really does need more bridges.
- More choice, not a mass move. When the new bridges open, more people will move across, because it will be easier to get around and homes can be cheaper than in the inner city. But most people still want to live near the centre and its amenities.
- Tu Lien and Nhat Tan will share the load. In our view Nhat Tan will remain the road to Noi Bai airport, while Tu Lien will become the route towards the new Gia Binh airport and Bac Ninh.
Frequently Asked Questions
Which new bridges are being built across the Red River in Hanoi?
Seven: Tran Hung Dao, Tu Lien, Ngoc Hoi, Thuong Cat, Van Phuc, and Hong Ha and Me So on Ring Road 4. All started in 2025, and the city wants most of them open in 2027.
When will the Tu Lien bridge open?
The city’s latest target is a technical opening before 2 September 2027, ahead of the APEC meetings in Hanoi; some earlier reports gave 10 October 2027. The project was 26.85% complete by contract value at the end of October 2026.
When will the Tran Hung Dao bridge open?
The deadline is before 30 June 2027. It is the most advanced of the seven, at 54.2% by contract value in early November 2026. It will link the Hoan Kiem area directly with Long Bien.
Which bridges can I use today to cross the Red River by car?
From the centre to Long Bien, mainly Chuong Duong and the two Vinh Tuy bridges; Long Bien bridge carries only motorbikes, bicycles and trains. To Dong Anh and Noi Bai airport, most drivers use Nhat Tan or Thang Long bridge. Chuong Duong, Vinh Tuy and increasingly Nhat Tan are congested at peak hours.
How many bridges will cross the Red River in Hanoi?
The transport plan to 2030 counts 18 Red River bridges, about half of them already built, and the city has since added proposals for more. The 100-year master plan also prioritises road and metro tunnels under the river.
Will the new bridges make Dong Anh and Long Bien more popular with foreigners?
We expect more interest, because crossing the river will be faster. But we do not expect a mass move: most foreign residents still prefer to live close to the centre, and the new bridges mainly add choice and lower prices across the river.
Who is building the Tran Hung Dao bridge?
A consortium led by Sun Group, under a public-private partnership worth about VND 16.2 trillion. Construction started on 9 October 2025.
Sources
- Bridges: CafeF / Tien Phong (10 November 2026, citing Report 821/BC-SXD), CafeF / Ha Noi Moi (20 October 2026), CafeF / Ha Noi Moi (3 November 2026), CafeF / Tien Phong (21 October 2026), CafeF / Tien Phong (3 November 2026), VietnamFinance (12 July 2026), Nha Dau Tu (19 May 2025), The Investor (December 2025), VnExpress (30 August 2023), Vinhomes Market (20 November 2026)
- Plans: VietnamPlus (May 2026), Tien Phong
- Market: Phap Luat / Savills (23 March 2026)
Thinking about living across the river?
Tell us where you work and your budget. We will tell you honestly how long the commute takes today, what changes when the new bridges open, and which buildings in Long Bien or Dong Anh are worth a look.
About the author
Harry Nguyen is Co-Founder and Executive Director of Kensington Vietnam and a licensed real estate broker (certificate HN-2621, Hanoi Department of Construction). For more than 10 years he has helped foreigners rent and buy homes in Hanoi. Harry’s profile and listings
Update log: 27 November 2026 – first published, with a status tracker for every new Red River bridge.